How to create a milestone
A milestone marks an important point or event in projects. Milestones can only be 1 day long and they cannot have performers. Milestones can have dependencies or tasks dependent on a milestone. Revenue items can be related to milestones.
- Go to Projects & services > Projects.
- Click on the Name of a project.
- In the Project space, go to Tasks tab.
- Click New Task.
- Add Name, set Type as Milestone and add Start date.
- Fill in other necessary information.
    - 
        Select a task to the Depends on field, if this is dependent on another task. Note: If milestone is dependent on another task, Start date will be automatically set to start after the end of the selected task. 
 
- 
        
- Click Save as new.
 
           
           
            