How to create a milestone
A milestone marks an important point or event in projects. Milestones can only be 1 day long and they cannot have performers. Milestones can have dependencies or tasks dependent on a milestone. Revenue items can be related to milestones.
- Go to Projects & services > Projects.
- Click on the Name of a project.
- In the Project space, go to Tasks tab.
- Click New Task.
- Add Name, set Type as Milestone and add Start date.
- Fill in other necessary information.
-
Select a task to the Depends on field, if this is dependent on another task.
Note: If milestone is dependent on another task, Start date will be automatically set to start after the end of the selected task.
-
- Click Save as new.