How to manage work schedules – PlanMill Help – PlanMill is a SaaS and On-premise ERP for professional service business. This site is for users, administrators and partners

How to manage work schedules

Workflow

Before planning resources with Work schedules, check that you have valid information in the projects you are scheduling:

  • Tasks or requests exist and there deadlines are valid.
  • Assignments (correct performers assigned to the task).
  • All users assigned as performers have valid calendars for the planning period. Otherwise work schedules will show 0 hours for the persons.

Note: You can schedule in day, week or month view. Choose the one best suited for your company needs. Stick to that for the whole company (recommended).

Planned and remaining hours for a task

You can insert planned or remaining values for the assignment from the Project space (Task or Assignment tabs). The table cells will show the remaining value divided to the whole period of the task. See example assigned to Doe, Jack where planned amout of work is 60 and remaining is 60 h. Scheduled 0 h means that no one has yet edited the scheduling manually from the Work schedules.


Task/Assignment Start Finish Planned Accepted Remain
Product demo/Doe, Jack 01.06.2017 22.09.2017 60 h 0 60 h


Note:

  • Planned and Remain will show same amounts before any actual hours have been reported.
  • Planned and Remain will also be updated to Project space Task and Assignments tabs, Time sheet and reports.

    alt text

How to change the scheduled work amounts in Work schedules

In case the project manager decides that the work is not distributed as it should, the scheduled work can be changed manually. After manual editing Work schedules will look like below. Scheduled is changed to 60 hours, because user has manually changed the scheduling. Planned and remaining amounts for the assignment will remain as 60 hours because the amount has not changed and the same amount was scheduled.


Task/Assignment June July August September Scheduled
Product demo/ Doe, Jack 01.06.2017-22.09.2017 20 h 10 h 10 h 20 h 60 h


alt text

Scheduling and planning only from Work schedules

In some cases it is more convenient to assign performers with 0 hours planned and remaining in the Project space. That is for example with continuous services with resourcing needs in only a few periods of the year. Scheduling is done directly from Work schedules. Below is example with Brooke, Simon which has initially both planned and remaining hours set as zero.


Task/Assignment June July August September Scheduled Assignment
R&D/ Brooke, Simon 01.06.2017-22.09.2017 0 0 0 0 0 Planned: 0 h Actual: 0 h Remain: 0 h


Editing the values will also change the assignment planned and remain values (also in Project space). After actual has become > 0 h only remain is changed from manual scheduling. Actual means the amount of accepted time reports for this particular assignment. After scheduling manually the assignment will look like below.

alt text

At the same time the view at the Project space Tasks tab looks like below.

alt text

Editing remaining amount or start and finish dates of the task/assignment

Changing the remaining amount or deadlines of an task/assignment causes the manual scheduling to be out of sync with the new values.

  1. When saving changes, a dialog window will ask if the manual scheduling is going to be removed or not.
    • If you click Yes the new remaining amounts will be divided evenly across all periods of the assignment.
    • If you click No the manual scheduling will be kept intact, but the Remain value will be different.

    Note: When the start or finish dates are edited all scheduling outside the task’s new dates will be deleted.

alt text

Picture from the Work schedules after changing the assignments amounts for Brooke, Simon and not removing the manually scheduled hours. If we had clicked Yes to remove the manually scheduled hours, new values to the cells would have been set according to the new planned amount.

alt text

Still have questions? We're happy to help Contact Us